KP’s Four Hydropower Projects in Pakistan Delayed By Three Years

 Khyber Pakhtunkhwa’s four 244.4 MW renewable and cheap electricity hydropower projects are stalled due to negligence of the Ministry of Energy (Power Division) and PESCO for the last three years.

The projects are pending due to non-approval, notification, import certificates, and purchase agreement. Similarly, Pakhtunkhwa Energy and Development Organisation (PEDO) has an arrear of Rs7,147.604 million in electricity sales to the federal government. A reliable government source told this correspondent that the projects were delayed due to bureaucratic hurdles, which are hampering the production of cheap electricity, while Prime Minister Imran Khan is focusing on cheap hydropower generation in the country. Ongoing hydropower projects are also being affected due to non-payment of dues.

According to documents available with this correspondent, the PEDO for the first time in Pakistan for hydropower projects conducted internationally competitive bidding in February 2016 for six projects of 518 MW based on the lowest trellised tariff. After evaluation, M/s Master Hydro was recommended as the first ranked bidder for 99 MW Arkari Gol HPP and M/s Saifco Energy for 102 MW Shigo Kas HPP.

However, the tariff for 102 MW Shigo Kas HPP was approved in February 2018 while 99 MW Arkari Gol HPP was approved in June 2018 by Nepra. The Nepra has shared the approved tariffs with the Ministry of Energy (Power Division) for notification in the Official Gazette of Pakistan. However, the Ministry of Energy (Power Division) notification is not yet issued despite all possible follow up by the KP government.

pakistan hydropower

Likewise, import of machinery of 40.8 MW Koto HPP is pending since January 2020 due to non-issuance of import certificate although the generation licence has been issued and tariff determined by Nepra. Moreover, under the Fifth Schedule Custom Act 1969, the Power Division federal Ministry of Energy is supposed to issue import certificates for those hydropower projects which will supply electricity to the national grid. Due to the non-supply of machinery, the project could not be commissioned. Some of the machinery got auctioned in April 2021 at the Karachi port due to delays and the progress on project suffered badly. Similarly, another 2.6 MW Machai project was completed in November 2017 but PESCO has not signed a purchase agreement without any justification.

On the other hand, the federal government has to pay arrears of Rs 2767.172 million of Malakand 3 Hydro Power Project (HPP), Rs124.77 million, Machai, Rs191.04 million of Ranolia HPP, Rs2,779.48 million, Daral Khawar, and Rs1285.142 million of Pehur HPP to PEDO.

According to available data, the federal government has to pay arrears amounting to Rs1286 million for the Malakand 3 hydropower project. In addition to that indexation claim of Malakand 3 amounting to Rs 1,481.172 million is also pending notification in the Power Division.

The 2.6 MW Machai project was completed in November 2017. PEDO has sold electricity at the rate of Rs5.469 kWh since the inception of the project. Around an arrear of Rs124.7 million is pending against Wapda.

Similarly, the 36.6 MW Daral Khwar project started generation in April 2019 with a tariff rate of Rs8.437 per kWh. An amount of Rs2779.48 million is outstanding against the federal government. Another 17 MW Ranolia, project was commissioned in February 2020 and the rate was fixed at Rs4.0147, however, an amount of Rs191.04 million is pending towards Central Power Purchasing Agency (CPPA).

According to details, Pehur HP project was commissioned in March 2010 but the federal government has paid only Rs3 billion and an arrear of Rs1285.142 million is yet to be paid to PEDO.

PEDO Chief Executive Muhammad Naeem told this correspondent that KP has a huge potential to generate more than 30,000 MW of hydro power and the provincial government is providing all resources to PEDO to generate cheap electricity from the province. The hydro projects are a source of affordable energy and a major source of revenue for the province.

He said PEDO has already registered certain hydro potential raw sites of 711 MW to the private sector investors on a first-come-first served basis under the KP hydropower policy 2016. However, further process was stalled due to the suspension of the KP hydropower policy 2016 by the Peshawar High Court in November 2018. Later on, the litigation was successfully concluded in December 2020. Two LOIs have been issued to the Korean state-owned companies under G2G arrangements for the development of 215 MW Asrit-Kedam HPP in IPP mode 496 MW Lower Spat Gah HPP. These projects will be initiated in due course of time after completing codal formalities.


评论

此博客中的热门博文

Get to know China’s wind farms —— Inner Mongolia Ulanqab Wind Farm(wind power)

  Introduction Inner Mongolia is the richest region in China in terms of wind resources and the closest to the country's electricity load, making it ideal for the development of mega wind power bases. Because of its unique wind resources, it has become a haven for investment companies to capture wind power projects. The most representative of these projects is the first phase of the Wulanchabu wind power project, which is the pinnacle of China's wind power industry. Construction time: On September 26, 2019, the world's largest single onshore wind farm, the first phase of the 6 million kilowatt demonstration project of the Ulanqab Wind Power Base, officially began construction.   Total investment: The Wulanchabu Wind Power Base Phase I 6 million kilowatt demonstration project is the first wind power project to be included in the national plan for clean energy parity outbound transmission, with a total static investment of 36.1 billion yuan, making it the largest single onsho...

Water Turbine Design for Small Scale Hydro Energy

                                                  https://www.boland-hydroturbine.com/ Selecting the Best Type of Water Turbine Design Selecting the best type of water turbine design for your particular situation often depends on the amount of head and flow rate that is available at your particular location and whether it is at the side of a river or stream, or the water is to be channelled or piped directly to your location. Other factors include whether you want an enclosed “reaction turbine design” such as the Francis turbine or an open “impulse turbine design”, such as the Pelton turbine as well as the speed of rotation of your proposed electrical generator. By analysing all of these factors together you can get some indication of what type of  Water Turbine Design  may work best for your particular situation. Knowing the difference between ...

Get To Know China's Hydropower Plants----Huangdeng Hydropower Station

 Introduction At 00:00 on January 1, 2019, four units of Dahuabiao, Huangdeng, Wulonglong and Lidi hydropower stations with a total of 1,092,500 kilowatts were successfully put into operation.  The four units put into operation on the same day once again refreshed the world hydropower  commissioning record of "one-day double commissioning" set by the company on July 12, 2018.  So far, all eight units of Huangdeng and Dahuaqiao hydropower stations have been put into operation. The total installed capacity has reached 24,992,800 kilowatts, the asset size has exceeded 180 billion yuan, and the cumulative power generation has exceeded 570 billion kilowatt hours. Geographic location. Huangdeng Hydropower Station is located in Lanping County, Nujiang Prefecture, Yunnan Province. It is developed by dike and dam, and is the fifth stage hydropower station in the hydropower ladder development program of the upper reaches of the Lancang River in Yunnan Province from Gushui to M...