跳至主要内容

CTG Put All 96 Hydro Turbine Units Into Operation Recently

 

China Three Gorges Corporation (CTG) has announced that its six cascade hydropower plants along the main stream of the Yangtze River put all of their 96 power units into operation on 7 July as part of its efforts to meet the peak demand of the grid in the summer, the first time that all the power generators have been in operation simultaneously.

The total power generated from the cascade hydropower plants – Three Gorges, Gezhouba, Xiluodu, Xiangjiaba, Wudongde and Baihetan – reached 52GW on the day.


The total power generated by the cascade power stations from June 11 to July 6 reached 17.85 billion kWh, securing electricity supply in Guangdong and Zhejiang provinces. With all the power units of Wudongde hydropower plant and the first units of Baihetan hydropower in operation, CTG now has six hydropower plants on the main stream of Yangtze River, with a total of 96 power units and a total installed capacity of 57.695GW as of June, up from 45.495GW at the beginning of last year.


CTG also recently announced that the tailrace fish collection and transport system at its Wudongde hydropower plant captured 10,000 wild fish in the Jinsha River between April and July 5, with a daily collection of nearly 2000 fish.


The fixed fish collection and transport system was installed at the tailrace outlet to protect the aquatic life in the Jinsha River and help the migration of rare and endemic fish in the area of Wudongde hydropower plant. The system, the first of its kind in China, has collected 45 species of fish so far, reaching its design objective and initially validating its feasibility.


评论

此博客中的热门博文

Baihetan Hydropower Station set to help with China’s carbon goal

  The Baihetan Hydropower Station has officially started storing water as the gate of number two diversion bottom hole closed on April 6, meaning the world's largest hydropower project under construction has taken a critical step toward the goal for the first batch of hydropower units to start generating electricity on July 1.  With the closing of the gate, the reservoir water level began to rise from 655 meters, according to a statement from Sinohydro Engineering Bureau 8 Co, adding that the reservoir water level will be stored to 775 meters in mid-June to meet the conditions for the first batch of hydropower-generating units to start operation. From August to September, the reservoir water will be stored to 800 meters, and then gradually stored to the normal storage level of 825 meters in June 2022. The total storage capacity of Baihetan Reservoir will be 20.627 billion cubic meters, which accounts for 91 percent of the Jinsha River Basin. The flood control reservoir is an i...

40.8MW Koto Hydropower Project To Be Completed by December

  About 90 per cent work on the under-construction Koto hydropower project (Koto-HPP) has been done and it will be completed by December this year, said assistant project director while briefing a team of the district administration. The team, including deputy commissioner Aun Haider Gondal, Timergara assistant commissioner Tahir Ali and other officials, visited the project site here the other day. Giving details, Koto-HPP assistant director Mohammad Shuaib said the powerhouse would generate 40.8MW of electricity that would be added to the national grid. He said that the remaining 10 per cent work on the project would be completed by coming December. He said work on the power tunnel had been completed by the contractor before its stipulated time. The deputy commissioner inspected various portions of the power station like box channel, surge shaft, sand trap and powerhouse and assured his full cooperation on part of his district administration for the timely completion of the projec...

Preparations for construction of 2400MW Batoka Gorge Hydropower Plant move a gear up

                                                        The Environmental and Social Impact Assessment (ESIA) disclosure process for the 4.5 billion U.S.   dollars Batoka Gorge Hydro-Electric Scheme (BGHES) has been completed, paving the way for the  implementation of the project, an official said Thursday. Chairperson of the Zambezi River Authority Council of Ministers, Zhemu Soda, who is also Zimbabwean Minister of Energy and Power Development, made the disclosure during the 38th Council of Ministers virtual meeting held Thursday. "It is encouraging to learn that most of the preparatory works for the implementation of the scheme have been completed. This includes the updating of the 1993 engineering feasibility studies and the undertaking of the environmental and social impact assessment (ESIA) studies which have culminated in the p...