40.8MW Koto Hydropower Project To Be Completed by December


 About 90 per cent work on the under-construction Koto hydropower project (Koto-HPP) has been done and it will be completed by December this year, said assistant project director while briefing a team of the district administration.

The team, including deputy commissioner Aun Haider Gondal, Timergara assistant commissioner Tahir Ali and other officials, visited the project site here the other day.

Giving details, Koto-HPP assistant director Mohammad Shuaib said the powerhouse would generate 40.8MW of electricity that would be added to the national grid.

He said that the remaining 10 per cent work on the project would be completed by coming December. He said work on the power tunnel had been completed by the contractor before its stipulated time.

The deputy commissioner inspected various portions of the power station like box channel, surge shaft, sand trap and powerhouse and assured his full cooperation on part of his district administration for the timely completion of the project.

Mr Shuaib said the objective of the scheme was to develop power potential in Khyber Pakhtunkhwa on a sustainable basis to provide environment-friendly energy to the consumers.

Work on the project was started in Feb 2015 and according to its contract it was to be completed in Feb 2019.

The project was jointly identified by the Pakhtunkhwa Energy Development Organisation (Pedo) and GTZ Germany in 1992.

He said that the Executive Committee of the National Economic Council approved the project on Aug 18, 2014, with a revised cost of Rs13.9 billion while the contract was awarded on Dec 10, 2014.

Talking to this correspondent, a resident of the area Amjad Ali Shah claimed that several dates for completion had been announced earlier by the authorities, but the project was yet to be completed.

FEUD SETTLED: A jirga of elders on Sunday settled a blood feud between two families in Munda area of Jandol.

Last year, a business dispute between the residents of Gosam and Dandoshah areas had led to a firing incident in which five people, including four from one family and one person from the other, were killed.

With the efforts of jirga leaders, the two parties came to the table and held talks. The jirga led by JI district chief Izazul Mulk made efforts to convince the parties to end enmity, which succeeded in the end.

Dawn

评论

此博客中的热门博文

Water Turbine Design for Small Scale Hydro Energy

                                                  https://www.boland-hydroturbine.com/ Selecting the Best Type of Water Turbine Design Selecting the best type of water turbine design for your particular situation often depends on the amount of head and flow rate that is available at your particular location and whether it is at the side of a river or stream, or the water is to be channelled or piped directly to your location. Other factors include whether you want an enclosed “reaction turbine design” such as the Francis turbine or an open “impulse turbine design”, such as the Pelton turbine as well as the speed of rotation of your proposed electrical generator. By analysing all of these factors together you can get some indication of what type of  Water Turbine Design  may work best for your particular situation. Knowing the difference between a Pelton and Francis turbine for example, will help make the choice easier. The following table gives a basic idea of which particul

Types of Hydropower Plants

                                                   There are three types of hydropower facilities: impoundment, diversion, and pumped storage. Some hydropower plants use dams and some do not. The images below show both types of hydropower plants. MPOUNDMENT The most common type of hydroelectric power plant is an impoundment facility. An impoundment facility, typically a large hydropower system, uses a dam to store river water in a reservoir. Water released from the reservoir flows through a turbine, spinning it, which in turn activates a generator to produce electricity. The water may be released either to meet changing electricity needs or to maintain a constant reservoir level.                                                www.boland-hydroturbine.com DIVERSION A diversion, sometimes called run-of-river, facility channels a portion of a river through a canal or penstock. It may not require the use of a dam. PUMPED STORAGE Another type of hydropower called pumped

Hydropower, the only solution for cheapest power generation

                                                 https://www.boland-hydroturbine.com/ Hydropower has the lowest life-cycle cost of any power generation technology. Hydropower is a potential life-saver for Pakistan. Yet its development has been hampered for decades. Hence, only 15 percent of Pakistan’s over 60,000MW hydropower potential has been developed in 70 years. Hydropower plants power generation can give a country economy a new path of progress. Despite initial costs and long gestation periods, hydropower plants have almost no fuel cost and have operational lives of over a century. New hydropwer plants generate electricity at Rs6-10 per unit compared to thermal power plants’ Rs15-25 per unit. All other power-generating technologies have up to 30 years of project life and need up to four times expensive plant replacements in foreign exchange. Wind and solar technologies are solely dependent on the weather. They can at best supplement but not replace hydropower which, amo