跳至主要内容

Cambodian Cabinet reviews 150MW hydropower project

 

The Council of Ministers on Wednesday said it will review a proposed 150MW hydropower project on the upper reaches of the Tatai River in Koh Kong province’s northern Thma Bang district.

Proposals for a 500kV transmission line connecting Phnom Penh to the Cambodia-Lao border and another one linking Battambang province with the Cambodian-Thai border will also be on the agenda when the Council of Ministers convenes on Friday.

Victor Jona, the director-general of the Ministry of Mines and Energy’s General Department of Energy, told The Post that the proposals were submitted to the Council of Ministers following completion of their associated environmental and social impact assessments.

He voiced his approval for the project and said minister Suy Sem would back it at the meeting.

He said one of the transmission lines would deliver electricity from a coal-fired power plant in Laos, as outlined in a purchase agreement that Cambodia signed last year. The other line would import power from Thailand.

“We will first seek approval at the Council of Ministers meeting. Then, we will negotiate investment costs and project implementation agreements that will be signed between the Ministry of Mines and Energy and the company.

“This is in addition to the power transmission fee that state-run energy supplier Electricite du Cambodge [EdC] will negotiate with the company,” he said.

Provincial deputy governor Sok Sothy told The Post in June that the hydropower project will be built by the Chinese state-owned China National Heavy Machinery Corp (CNHM) at a cost of $380 million and will supply Koh Kong and neighbouring provinces.

“The project will not only spur development in Koh Kong province, but it will also serve as a battery for electricity distribution throughout Cambodia in the future,” said Sothy.

There are currently three hydropower dams in the province generating 602MW, he said. Russey Chrum Krom produces 338MW, Stung Tatai provides 246MW and Kirirom III adds 18MW.

At a meeting on October 9, the Council of Ministers approved the draft of a $12.796 billion three-year rolling public investment programme (2021-2023).

The minutes of the meeting show that the government will use the investment to fund a total of 629 projects.

The government will spend $8.4 billion on 203 ongoing projects and $4.4 billion on 426 new projects as it works on implementing the National Strategic Development Plan 2019-2023.

About 8.9 per cent of the total budget will be disbursed for social projects, 34.2 per cent for economic projects, 50.1 per cent for infrastructure projects and 6.8 per cent for services and inter-sectoral projects.

THOU VIREAK

评论

此博客中的热门博文

Baihetan Hydropower Station set to help with China’s carbon goal

  The Baihetan Hydropower Station has officially started storing water as the gate of number two diversion bottom hole closed on April 6, meaning the world's largest hydropower project under construction has taken a critical step toward the goal for the first batch of hydropower units to start generating electricity on July 1.  With the closing of the gate, the reservoir water level began to rise from 655 meters, according to a statement from Sinohydro Engineering Bureau 8 Co, adding that the reservoir water level will be stored to 775 meters in mid-June to meet the conditions for the first batch of hydropower-generating units to start operation. From August to September, the reservoir water will be stored to 800 meters, and then gradually stored to the normal storage level of 825 meters in June 2022. The total storage capacity of Baihetan Reservoir will be 20.627 billion cubic meters, which accounts for 91 percent of the Jinsha River Basin. The flood control reservoir is an i...

Preparations for construction of 2400MW Batoka Gorge Hydropower Plant move a gear up

                                                        The Environmental and Social Impact Assessment (ESIA) disclosure process for the 4.5 billion U.S.   dollars Batoka Gorge Hydro-Electric Scheme (BGHES) has been completed, paving the way for the  implementation of the project, an official said Thursday. Chairperson of the Zambezi River Authority Council of Ministers, Zhemu Soda, who is also Zimbabwean Minister of Energy and Power Development, made the disclosure during the 38th Council of Ministers virtual meeting held Thursday. "It is encouraging to learn that most of the preparatory works for the implementation of the scheme have been completed. This includes the updating of the 1993 engineering feasibility studies and the undertaking of the environmental and social impact assessment (ESIA) studies which have culminated in the p...

40.8MW Koto Hydropower Project To Be Completed by December

  About 90 per cent work on the under-construction Koto hydropower project (Koto-HPP) has been done and it will be completed by December this year, said assistant project director while briefing a team of the district administration. The team, including deputy commissioner Aun Haider Gondal, Timergara assistant commissioner Tahir Ali and other officials, visited the project site here the other day. Giving details, Koto-HPP assistant director Mohammad Shuaib said the powerhouse would generate 40.8MW of electricity that would be added to the national grid. He said that the remaining 10 per cent work on the project would be completed by coming December. He said work on the power tunnel had been completed by the contractor before its stipulated time. The deputy commissioner inspected various portions of the power station like box channel, surge shaft, sand trap and powerhouse and assured his full cooperation on part of his district administration for the timely completion of the projec...