跳至主要内容

Hydropower Producers Resisting Tariff Cut

 












ISLAMABAD: As the government struggles to translate memorandums of understanding (MOUs) sigend with the Independent Power Peoducers(IPPs) of thermal and renewable power plants for tariff discounts into contracts, sponsors of hydropower power plants (HPPs) have declined to revise old agreements with the government.

A senior government official told Dawn that sponsors of HPPs had three to four sessions with the IPPs negotiations committee led by former federal secretary Babar Yaqoob and comprising members of stakeholders and agencies appointed by the government to negotiate power contracts. However, nothing had been finalised yet, he said.

Sources close to HPPs confirmed “they refused to sign MOUs prepared by the negotiation committee” because the government was applying a “broad brush to all IPPs irrespective of technology” (furnace oil, gas, coal, solar and wind etc) and seeking reduction of equity return, operation and maintenance expenses and others even though all power generating technologies were different.

These sources said that thermal, wind and solar power plants comprised 85-90pc plant & machinery cost and the balance 10-15pc as civil works but hydropower on the other hand comprised about 80pc of civil works and the remaining 20pc as plant and machinery cost. That is why the HPPs had long gestation period of 6-8 years unlike 2-3 three years of other technologies.

Hydropower, with the highest civil works content of any power generating technology had advantages for the local economy, job creation and boosting local construction materials industries but due to the high civil works content the final construction cost becomes unpredictable. Most of the hydropower projects worldwide suffered a degree of cost overrun as such projects, notwithstanding the preliminary design involved design-built arrangements.

The government team was told that National Electric Power Regulatory Authority (Nepra) only allowed specified and earmarked cost, the cost overruns end up being disallowed and borne by the sponsors, thus immediately reducing the equity return. The Nepra generally allowed allows a 17pc internal rate of return (IRR) but sponsors insist that no HPP ever achieved this and mostly end up with 11-13pc IRR.

“Given the massive risks hydropower construction entailed including hydrological risk, seismic and geological risk, remote locations and accessibility issues, the effective IRR of 12-13pc was already lower than all other technologies even after their revised rates under fresh MOUs.

“Hydropower required a high equity return of no less than 17pc to attract investors who enter with an appreciation of the multitude of construction risks and the strong likelihood that their equity return will fall below this level,” said a source associated with an HPP, adding that starting off a hydropower project lower than 17pc was not an option if hydropower was a priority area.

He said the IPP committee would have to fine-tune its approach and consider each generating technology separately with an eye on future investment required in the sector. At present three HPPs of about 340MW were in operation while 10 HPPs, some of them under China-Pakistan Econo­mic Cooperation — are under construction with targeted completion of 3,750MW in 2027 and 1,200MW in 2028.

DAWN

评论

此博客中的热门博文

Baihetan Hydropower Station set to help with China’s carbon goal

  The Baihetan Hydropower Station has officially started storing water as the gate of number two diversion bottom hole closed on April 6, meaning the world's largest hydropower project under construction has taken a critical step toward the goal for the first batch of hydropower units to start generating electricity on July 1.  With the closing of the gate, the reservoir water level began to rise from 655 meters, according to a statement from Sinohydro Engineering Bureau 8 Co, adding that the reservoir water level will be stored to 775 meters in mid-June to meet the conditions for the first batch of hydropower-generating units to start operation. From August to September, the reservoir water will be stored to 800 meters, and then gradually stored to the normal storage level of 825 meters in June 2022. The total storage capacity of Baihetan Reservoir will be 20.627 billion cubic meters, which accounts for 91 percent of the Jinsha River Basin. The flood control reservoir is an i...

40.8MW Koto Hydropower Project To Be Completed by December

  About 90 per cent work on the under-construction Koto hydropower project (Koto-HPP) has been done and it will be completed by December this year, said assistant project director while briefing a team of the district administration. The team, including deputy commissioner Aun Haider Gondal, Timergara assistant commissioner Tahir Ali and other officials, visited the project site here the other day. Giving details, Koto-HPP assistant director Mohammad Shuaib said the powerhouse would generate 40.8MW of electricity that would be added to the national grid. He said that the remaining 10 per cent work on the project would be completed by coming December. He said work on the power tunnel had been completed by the contractor before its stipulated time. The deputy commissioner inspected various portions of the power station like box channel, surge shaft, sand trap and powerhouse and assured his full cooperation on part of his district administration for the timely completion of the projec...

All units of world’s seventh largest hydropower station put into operation in China

  All units of the Wudongde Hydropower Station will officially be put into operation on Wednesday, reducing carbon dioxide emissions by 30.5 million tons per year, China Central Television (CCTV) reported on Wednesday.  Becoming the seventh largest hydropower station in the world with the largest single unit capacity in operation, the power station is equipped with a capacity of 10.20 million kilowatts, CCTV reported, adding that the annual growth rate will reach 38.91 billion kilowatt-hours once the hydropower station being fully put into operation, the equivalent of saving 12.20 million tons of standard coal and reducing 30.50 million tons of carbon dioxide emissions every year.  Wudongde Hydropower Station is designed as a concrete double-curved arch dam with a maximum height of 270 meters. The foundation bed of the dam is only 51.41 meters thick, which makes the hydropower station the thinnest 300-meter arch dam in the world at present. The first series generator sets...