跳至主要内容

Large storage potential in future ice-free glacier basins

Global warming will cause substantial glacier retreat for the majority of the world’s glaciers over the next few decades. This will not only spell the end for some magnificent natural monuments, but also importantly affect the water cycle. In high- mountain regions, these ice masses act as reservoirs feeding water to large river systems, and balancing seasonal discharges.
Without glaciers, rivers would carry considerably less water in summer, which would have noticeable consequences for water availability, energy production and agriculture in many regions of the world. Researchers had previously discussed the idea of compensating the shrinking storage function of glaciers with reservoirs (see Zukunftsblog – in German only).
A group of glaciologists from ETH Zurich and the Swiss Federal Institute for Forest, Snow and Landscape Research WSL is now again engaging in the discussion about the dwindling ice: in a study published in Nature, they investigate the global potential for storing water and producing hydropower in presently- glacierised areas that will become ice- free within this century.
The Gebidem arch dam in Switzerland is partially fed by meltwater from the Aletsch Glacier, the longest glacier in the Alps.
The Gebidem arch dam in Switzerland is partially fed by meltwater from the Aletsch Glacier, the longest glacier in the Alps                                             www.boland-hydroturbine.com
(The Gebidem arch dam in Switzerland is partially fed by meltwater from the Aletsch Glacier, the longest glacier in the Alps)

Using glaciers as reservoirs

In their study, the research team around Daniel Farinotti, Professor of Glaciology at the Laboratory of Hydraulics, Hydrology and Glaciology (VAW) at ETH Zurich and at WSL, analysed about 185,000 glaciers. For these sites they calculated a maximum theoretical storage potential of 875 cubic kilometers (km3) and a maximum theoretical hydropower potential of 1350 terawatt hours (TWh) per year.
“This theoretical total potential corresponds to about one third of current hydropower production worldwide. But in reality, only part of it would be realisable”, explains Farinotti.
In order to obtain a more realistic estimate, the researchers conducted an initial suitability assessment for all sites. They identified around 40 percent of the theoretical total potential as “potentially” suitable, equalling to a storage volume of 355 km3 and a hydropower potential of 533 TWh per year. The latter corresponds to around 13 percent of the current hydropower production worldwide, or nine times Switzerland’s annual electricity demand.
“Even this potentially suitable storage volume would be sufficient to store about half of the annual runoff from the studied glacierised basins,” Farinotti says. Assuming an average climate scenario, about three- quarters of the storage potential could become ice- free by 2050.

Cautious estimate of potential

For their analysis, the glaciologists used a global glacier inventory and placed virtual dams at the current terminus of each glacier with an area of more than 50,000 square meters located outside the Subantarctic. They then optimised the size of the reservoirs by appropriate dam positioning and height. In doing so, they minimised the reservoirs’ impact on the landscape and did not just maximise economic return. The team used digital elevation models of the subglacial terrain and combined them with a glacier evolution model to determine the storage volume of the 185,000 glaciers they had selected.
In the suitability analysis that followed, the researchers assessed the sites based on several ecological, technical and economic criteria: “On this basis, we ruled out the most unsuitable sites; this enabled a more realistic assessment,” explains co- author Vanessa Round, who was affiliated at both institutions and had a pivotal role in the study. She also adds that it is neither realistic nor desirable to build a dam for every glacier.

A model for the future?

The team also stresses that local impacts should be assessed on a case- by-case basis. Nevertheless, the results indicate that deglacierised basins could significantly contribute to national energy supply and water storage in a number of countries, particularly in High Mountain Asia.
Among the countries with the largest potentials are Tajikistan, where the calculated hydropower potential could account for up to 80 percent of current electricity consumption, Chile (40 percent) and Pakistan (35 percent). In Canada, Iceland, Bolivia and Norway, the potential equals 10–25 percent of their current electricity consumption. For Switzerland, the study shows a potential of 10 percent.
Meanwhile, the Swiss Federal Office of Energy has recently revised downwards the expansion potential for Swiss hydropower. This is mainly because of revised estimates for the impact of stricter regulations on environmental flows, and because the potential of small- scale hydropower is now considered to be lower than it was in 2012. However, in its assessment, the SFOE explicitly excluded the hydropower potential that could arise from future ice- free basins. For this reason, the glaciologists led by Farinotti do not see a contradiction to their results, as the two studies cannot be directly compared.
 ETH Zurich

评论

此博客中的热门博文

Baihetan Hydropower Station set to help with China’s carbon goal

  The Baihetan Hydropower Station has officially started storing water as the gate of number two diversion bottom hole closed on April 6, meaning the world's largest hydropower project under construction has taken a critical step toward the goal for the first batch of hydropower units to start generating electricity on July 1.  With the closing of the gate, the reservoir water level began to rise from 655 meters, according to a statement from Sinohydro Engineering Bureau 8 Co, adding that the reservoir water level will be stored to 775 meters in mid-June to meet the conditions for the first batch of hydropower-generating units to start operation. From August to September, the reservoir water will be stored to 800 meters, and then gradually stored to the normal storage level of 825 meters in June 2022. The total storage capacity of Baihetan Reservoir will be 20.627 billion cubic meters, which accounts for 91 percent of the Jinsha River Basin. The flood control reservoir is an i...

40.8MW Koto Hydropower Project To Be Completed by December

  About 90 per cent work on the under-construction Koto hydropower project (Koto-HPP) has been done and it will be completed by December this year, said assistant project director while briefing a team of the district administration. The team, including deputy commissioner Aun Haider Gondal, Timergara assistant commissioner Tahir Ali and other officials, visited the project site here the other day. Giving details, Koto-HPP assistant director Mohammad Shuaib said the powerhouse would generate 40.8MW of electricity that would be added to the national grid. He said that the remaining 10 per cent work on the project would be completed by coming December. He said work on the power tunnel had been completed by the contractor before its stipulated time. The deputy commissioner inspected various portions of the power station like box channel, surge shaft, sand trap and powerhouse and assured his full cooperation on part of his district administration for the timely completion of the projec...

Preparations for construction of 2400MW Batoka Gorge Hydropower Plant move a gear up

                                                        The Environmental and Social Impact Assessment (ESIA) disclosure process for the 4.5 billion U.S.   dollars Batoka Gorge Hydro-Electric Scheme (BGHES) has been completed, paving the way for the  implementation of the project, an official said Thursday. Chairperson of the Zambezi River Authority Council of Ministers, Zhemu Soda, who is also Zimbabwean Minister of Energy and Power Development, made the disclosure during the 38th Council of Ministers virtual meeting held Thursday. "It is encouraging to learn that most of the preparatory works for the implementation of the scheme have been completed. This includes the updating of the 1993 engineering feasibility studies and the undertaking of the environmental and social impact assessment (ESIA) studies which have culminated in the p...