跳至主要内容

Four hydropower projects to continue implementation in 2019-2020 FY

                                             https://www.boland-hydroturbine.com/
The four hydropower projects—671-megawatt (MW) Shweli (3) hydropower project, 280-megawatt (MW) Upper Yehwa hydropower project, 111-megawatt (MW) Thahtay hydropower project and 51-megawatt (MW) Upper Kyaingtaung hydropower project—will continue implementations during 2019-2020 fiscal years, said a source from the Ministry of Electricity and Energy.
The projects we will continue implementing during 2019-2020 FY include 622.38 miles of 66-KV power lines, 22 66-KV sub-power plants, 132-KV, 230-KV, 500-KV, 1488.15 miles of power lines, 25 sub-power plants, 23-megawatt  Myanaung natural gas-fired power plant, 152-megawatt Ale Paunglaung hydropower project, 671-megawatt (MW) Shweli (3) hydropower project, 280-megawatt (MW) Upper Yehwa yydropower project, 111-megawatt (MW) Thahtay hydropower project and 51-megawatt (MW) Upper Kyaingtaung hydropower project, said Dr. Tun Naing, Deputy Minister of the Ministry of Electricity and Energy.Upper Yeywa hydropower project is situated on the dam built on Dokhtawaddy (Myitnge) 280-megawatt (MW) power plant is built and it generates 1,409 million kilowatt hours annually. It is aimed at distributing power to all parts of the country through Myanmar national grid. It is a type of roller compacted concrete (RCC). It can store 277,000 acre feet of water. A 38.73 percentage of the construction of the dam has been so far finished.     The whole project will be finished in 2020-2021 FY. Built on Dokhtawaddy (Myitnge), Yeywa hydropower project is generating 790-megawatt. 210-megawatt Namtu (Thibaw), 735 megawatt Ale Yeywa hydropower project and 60-megawatt Deedoke project are under implementation, according to the Ministry of Electricity and Energy.

Eleven

评论

此博客中的热门博文

Baihetan Hydropower Station set to help with China’s carbon goal

  The Baihetan Hydropower Station has officially started storing water as the gate of number two diversion bottom hole closed on April 6, meaning the world's largest hydropower project under construction has taken a critical step toward the goal for the first batch of hydropower units to start generating electricity on July 1.  With the closing of the gate, the reservoir water level began to rise from 655 meters, according to a statement from Sinohydro Engineering Bureau 8 Co, adding that the reservoir water level will be stored to 775 meters in mid-June to meet the conditions for the first batch of hydropower-generating units to start operation. From August to September, the reservoir water will be stored to 800 meters, and then gradually stored to the normal storage level of 825 meters in June 2022. The total storage capacity of Baihetan Reservoir will be 20.627 billion cubic meters, which accounts for 91 percent of the Jinsha River Basin. The flood control reservoir is an i...

40.8MW Koto Hydropower Project To Be Completed by December

  About 90 per cent work on the under-construction Koto hydropower project (Koto-HPP) has been done and it will be completed by December this year, said assistant project director while briefing a team of the district administration. The team, including deputy commissioner Aun Haider Gondal, Timergara assistant commissioner Tahir Ali and other officials, visited the project site here the other day. Giving details, Koto-HPP assistant director Mohammad Shuaib said the powerhouse would generate 40.8MW of electricity that would be added to the national grid. He said that the remaining 10 per cent work on the project would be completed by coming December. He said work on the power tunnel had been completed by the contractor before its stipulated time. The deputy commissioner inspected various portions of the power station like box channel, surge shaft, sand trap and powerhouse and assured his full cooperation on part of his district administration for the timely completion of the projec...

Preparations for construction of 2400MW Batoka Gorge Hydropower Plant move a gear up

                                                        The Environmental and Social Impact Assessment (ESIA) disclosure process for the 4.5 billion U.S.   dollars Batoka Gorge Hydro-Electric Scheme (BGHES) has been completed, paving the way for the  implementation of the project, an official said Thursday. Chairperson of the Zambezi River Authority Council of Ministers, Zhemu Soda, who is also Zimbabwean Minister of Energy and Power Development, made the disclosure during the 38th Council of Ministers virtual meeting held Thursday. "It is encouraging to learn that most of the preparatory works for the implementation of the scheme have been completed. This includes the updating of the 1993 engineering feasibility studies and the undertaking of the environmental and social impact assessment (ESIA) studies which have culminated in the p...